Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 46273 REL 114: 1983-319-00 EXP PIT TAG RESEARCH AND DEVELOPMENT
Project Number:
Title:
New Marking and Monitoring Technologies
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
46273 REL 114
Contract Title:
1983-319-00 EXP PIT TAG RESEARCH AND DEVELOPMENT
Contract Continuation:
Previous: Next:
46273 REL 101: 1983-319-00 EXP DEVELOP PIT TAG TECHNOLOGY
  • 46273 REL 129: 1983-319-00 EXP PIT TAG RESEARCH AND DEVELOPMENT
Contract Status:
Closed
Contract Description:
This project addresses how to expand the current fish-tracking technologies to enable the fisheries community to successfully carry out the actions, research, and monitoring activities outlined in the 2000, 2004, and 2008 BiOps, 2004 UPA, Fish and Wildlife Program, and 2003 systemwide passage summary.  The goal of the project is to satisfy these needs by developing interrogation systems that will collect data on migrating juvenile and adult salmonids through mainstem Columbia River Basin (CRB) dams including juvenile salmon transiting surface-bypass systems and all life-stages transiting small streams.  These fish-tracking technologies are then used to assess the effectiveness of management actions and strategies for recovery of ESA-listed fish populations.  For example, development of PIT-tag systems that will work in large streams or even rivers are essential for determining the effectiveness of all types of restoration programs on stock recovery supported by BPA.  In addition, these systems would help delineate the different types of interactions between hatchery and wild stocks in the field.  

Over the past few years, this project has been working on developing a PIT-tag system for spillways.  This development has had to overcome both technical and political barriers or setbacks which have delayed installation of a system.  A PIT-tag system was developed for Ice Harbor Dam, but the Corps was unable to obtain funding for this installation.  The lack of funding halted this development until late 2011, when NOAA and the action agencies agreed to install a system at Lower Granite Dam.  Progress on finishing the design of the specialized spillway or ogee transceiver was slowed when Destron was bought out by Allflex in 2011.   Tests at Pasco in 2011 of the first prototype transceiver showed that more work needed to be done for the PIT-tag system to work for the spillbay application.  Allflex appointed Biomark to lead the Destron engineering staff; this transition resulted in little work being done with the ogee transceiver until September 2012.  Testing of the prototype ogee transceiver in 2013 in Minnesota revealed lower read ranges than desired.  The transceiver also failed during a fish  test at the corner-collector.  Biomark has continued to work on improving the transceiver, and tests in 2014 showed better performance in the corner-collector system at Bonneville Dam. The transceiver has demonstrated consistency and solid performance during two separate evaluations in March and December 2015; we plan to test the final transceiver configurations with fish releases at BCC in April 2016.  During this contract, NOAA Fisheries will continue to work with both Biomark and PSMFC to make any necessary modifications to the ogee transceiver and investigate alternative antenna designs.  Tests will be conducted at both Pasco and the corner collector to demonstrate that the transceiver is acceptable.  We will continue to work with the Corps to finalize the design for the Lower Granite Dam installation.

With the finishing of the new multiplexing transceiver (IS3001, in-stream applications are entering a more mature phase of development. The past few years have resulted in the development of power systems and data-collection methods being finalized.  The new transceiver will yield new antenna designs; however there have been problems with the first round of installations as antennas that yielded high performance in the laboratory tanked once they were installed in the rivers.  NOAA Fisheries has been investigating along with Biomark and other agencies how to solve this.  This work will continue with this contract.  Once this is solved, NOAA Fisheries will evaluate other aspects of the new transceiver and explore how to utilize it to designs systems for large rivers.  We are also working with another group of NOAA researchers to explore designing a series of multiple antennas to use in the estuary instead of the current system of a large net being pulled with a set of PIT-tag antennas installed at the cod end of the net.

Within this project, we propose to develop technologies that help monitor the stocks at critical (if possible, all) life stages and critical locations.   For example, many juvenile salmonids now use unmodified spillbays, spillbays outfitted with temporary spillway weirs (TSWs) or removable spillway weirs (RSWs), and turbines during their migration, but we are unable to monitor them in these locations because they lack PIT-tag interrogation systems.  Consequently, we are collecting fewer data points for the different survival models.  Therefore, we are proposing to start or continue development programs for interrogation systems (tags, antennas, receivers, etc) that will enable us to monitor these migrating fish through these pathways.  

We will concentrate our efforts on two main research areas or work elements besides project administration:

1. Finish development of the spillway PIT-tag system
                         a)   Evaluate the ogee transceiver at BCC and Pasco.
                         b)   Oversee the manufacturing and delivery of final ogee transceivers for the Lower Granite installation  
                         c)   Investigate alternative antenna designs with new transceiver
                         d)   Work with the Corps, PSMFC, and Biomark in finalizing the Corps' installation drawings

2.             Continue the development of in-stream interrogation systems
                         a)   Evaluation of a new point-to-multipoint system for MTS
                         b)   Evaluate alternative interrogation technologies
Account Type(s):
Expense
Contract Start Date:
04/01/2016
Contract End Date:
03/31/2017
Current Contract Value:
$844,101
Expenditures:
$844,101

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR B: 119. Administration tasks for this project 01/15/2017 01/15/2017
Environmental compliance documentation C: 165. Environmental compliance review for PIT Tag and in-stream systems 06/30/2016 06/30/2016
Delivery of final ogee transceivers D: 156. Spillway PIT-tag system - development, evaluation, equipment 03/30/2017 03/30/2017
Data will be collected from research conducted on in-stream interrogation systems E: 156. Continue development of in-stream interrogation systems 12/31/2016 12/31/2016
Submit BiOp RPA Report in Taurus F: 202. BiOp RPA Report for CY 2016 03/15/2017 03/15/2017
Completed Annual Report G: 132. Progress Report for Proj 2001-003-00 covering (Jan 2010) to (Dec 2012) 03/30/2017 03/30/2017
Completed Annual Report H: 132. Second combined Progress Report for the period (Jan 1, 2016) to (Dec 31, 2016) 03/15/2017 03/31/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 04/01/2016
B 119 Administration tasks for this project 04/01/2016
C 165 Environmental compliance review for PIT Tag and in-stream systems 04/01/2016
D 156 Spillway PIT-tag system - development, evaluation, equipment 04/01/2016
E 156 Continue development of in-stream interrogation systems 04/01/2016
F 202 BiOp RPA Report for CY 2016
G 132 Progress Report for Proj 2001-003-00 covering (Jan 2010) to (Dec 2012) 04/01/2016
H 132 Second combined Progress Report for the period (Jan 1, 2016) to (Dec 31, 2016) 04/01/2016